The project organization works best when which of the following conditions are satisfied? I.Work tasks can be defined with a specific goal and deadline.
II.The job is typical and familiar to the existing organization.
III.The work contains interrelated tasks requiring specialized skills.
IV.The project is temporary but unimportant to long-term organizational success.
V.The project cuts across organizational lines.