Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates

question 88

Multiple Choice

Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.