Table 11-7 A Project Manager Calculated Early and Late Start and Finish

question 87

Multiple Choice

Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.
Table 11-7 A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.    -Consider the project summarized in Table 11-7.What is the slack for Activity D? A) 7 B) 5 C) 1 D) 0
-Consider the project summarized in Table 11-7.What is the slack for Activity D?


Definitions:

Materials

Physical substances or components used in the production of goods or in the execution of projects and services.

Workstation

A specific area or desk equipped with the necessary tools and technology for an individual to perform their job tasks.

Improve Workflow

To make enhancements in the process or set of processes through which work is accomplished, aiming for greater efficiency.

Breakeven Point

The level of production or sales at which total costs equal total revenue, meaning there is no profit or loss.

Related Questions