Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 3,5,and

question 68

Multiple Choice

Given an activity's optimistic,most likely,and pessimistic time estimates of 3,5,and 15 days,respectively,compute the PERT standard deviation for this activity.