Development of a New Deluxe Version of a Particular Software

question 70

Essay

Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks). Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks).   (a) What is the project completion date? (b) What is the total cost required for completing this project on normal time? (c) If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost? (a) What is the project completion date?
(b) What is the total cost required for completing this project on normal time?
(c) If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost?


Definitions:

Principal Place of Business

The primary location where a business entity's central operations and management are conducted.

Business Name

The official name under which a company or merchant conducts business, which may be different from its legal corporate name.

Ultra Vires Acts

Acts performed beyond the powers or authority granted to a corporation or an individual by law.

S Corporation

A special designation that allows corporations to pass income directly to shareholders and avoid double taxation.

Related Questions