Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 3,5,and

question 19

Multiple Choice

Given an activity's optimistic,most likely,and pessimistic time estimates of 3,5,and 13 days respectively,compute the expected time for this activity.