Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 2,10,and

question 74

Multiple Choice

Given an activity's optimistic,most likely,and pessimistic time estimates of 2,10,and 20 days respectively,compute the PERT variance for this activity.