Use the Earned Value Table for Project Terrace to Determine

question 65

Multiple Choice

Use the earned value table for Project Terrace to determine their schedule variance if all dollar amounts are in hundreds. Use the earned value table for Project Terrace to determine their schedule variance if all dollar amounts are in hundreds.   A)  $100 B)  $120 C)  $1,200 D)  $200