A Project Has the Activity Duration and Cost Information Indicated

question 10

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days?   A)  $253,000 B)  $237,000 C)  $216,000 D)  $207,000