Examlex

Solved

Project Test Bank Is Composed of Activities We Will Refer

question 7

Multiple Choice

Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity) . Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration, so activity C in the original project becomes two activities, C1 and C2, each of which last 7 days. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is difference in the late start time for activity C in the original project and activity C1 in the laddered project? Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity) . Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration, so activity C in the original project becomes two activities, C1 and C2, each of which last 7 days. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is difference in the late start time for activity C in the original project and activity C1 in the laddered project?   A)  3 B)  5 C)  7 D)  9


Definitions:

Judicial Review

The power of courts to assess the legality of acts or decisions made by government officials or agencies, ensuring they do not violate the constitution or legal statutes.

Pervasive Regulation

Extensive and widespread regulatory control within a particular industry or across various sectors.

Administrative Agency

A government body responsible for overseeing and implementing legislation in specific areas of public policy.

Federal Regulation

Laws or rules prescribed by federal agencies to govern activities and industries across the country.

Related Questions