An Activity Has an Optimistic Time Estimate of 7 Days,a

question 67

Multiple Choice

An activity has an optimistic time estimate of 7 days,a most likely estimate of 12 days,and a pessimistic estimate of 20 days.What is the expected standard deviation of the activity?