A Project Is Represented by the Activity Durations (Estimated at 90

question 96

Multiple Choice

A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the feeder buffer if this project is managed using critical chain methodology? A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the feeder buffer if this project is managed using critical chain methodology?   A) 9.0 B) 7.5 C) 4.5 D) 6.0


Definitions:

Day-To-Day Activities

The regular, everyday tasks or operations that are essential to the functioning of a business or individual.

Unlimited Liability

A legal structure in which the business owners are personally responsible for all of the company's debts and obligations.

General Partnership

A partnership that involves a complete sharing in both the management and the liability of the business.

Related Questions