All Five Members of a Project Team Add 20% to Their

question 1

Multiple Choice

All five members of a project team add 20% to their individual serial activities as a safety margin and submit their time estimates to the project manager.The manager adds the activity length estimates together and adds 20% for his personal safety margin.Then,anticipating a cut by top management,he adds another 20% to his final project estimate.Much to his surprise,top management cuts only 10% off his time estimate.How much of a cushion is now built into the project?


Definitions:

Singles

Individuals who are not married or in a romantic relationship.

Growing Old

The process of aging, marked by the gradual decline in physical and sometimes mental capacity, and the transition through various phases of life towards the end of the lifespan.

Dying Alone

The experience of passing away without the presence or support of loved ones or acquaintances.

Postponing Marriage

Choosing to delay marriage until a later age than traditionally observed.

Related Questions