A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour are productive. The time to perform each task and the tasks which precede each task are:
a. Draw a network diagram of precedence relationships.
b. Compute the required cycle time per unit in minutes.
c. Compute the theoretical minimum number of workstations required to produce 40 units per hour.
d. Balance this line using longest processing time.
e. What is the efficiency of the line obtained in part d?
Men
Refers to adult human males, typically characterized by higher levels of androgens and secondary sexual characteristics such as facial hair and a deeper voice than females.
Women
Adult human females, often highlighted in studies and discussions related to gender-specific topics in culture, science, and society.
Homosexual Orientation
A sexual orientation characterized by emotional, romantic, or sexual attraction to individuals of the same sex.
Men
Adult human males, typically characterized by higher levels of muscle mass and facial hair compared to women.
Q8: What are the two basic types of
Q27: A waiting-line system that meets the assumptions
Q33: Evaluating location alternatives by comparing their composite
Q45: A toy manufacturer has three different
Q48: Which of the following is not information
Q70: One result of concurrent engineering in product
Q86: The role of quality in limiting a
Q101: Which of the following is true regarding
Q102: Regal Marine's attempts to keep in touch
Q127: The phrase Six Sigma has two meanings.