A facility is trying to set up an assembly line, and has identified the various tasks, and their relationship to each other, as shown in the following table. They wish to produce 600 units per day, working two 8-hour shifts.
a. Draw a network diagram of precedence relationships.
b. Compute the required cycle time per unit in seconds.
c. Compute the minimum number of workstations required to produce 600 units per day.
d. Balance this line using longest processing time.
e. What is the efficiency of the line obtained in part d?
Premium Price
A pricing strategy where goods or services are sold at a higher price point due to perceived advantages, often related to quality or status.
Bond Quoted
The price or interest rate at which a bond is currently being sold or bought in the market.
Dollar Amount
A numerical monetary value denoted in the currency of the United States.
Interest Earned
The total amount of interest received by a person or entity on investments over a specific period of time.
Q2: ISO 9000 has evolved from a set
Q20: "Operators simply load new programs, as necessary,
Q39: Provide an example of the postponement strategy
Q40: Explain how a Pareto chart can identify
Q67: The first step, and a key element,
Q67: Suppose that a fast food restaurant wants
Q72: There are three work centers (A,
Q73: Which of the following is not among
Q75: A transportation problem that has more units
Q116: Process control is the use of information