A Work Cell Is Scheduled to Build 120 Digital Light

question 67

Essay

A work cell is scheduled to build 120 digital light processor (DLP) assemblies each week. These assemblies are later installed into home theatre projection systems. The work cell has 7.5 hours of productive work each day, six days per week. What is takt time for this cell?