An Assembly Line with 11 Tasks Is to Be Balanced

question 88

Essay

An assembly line with 11 tasks is to be balanced. The longest task is 3 minutes, the shortest task is 0.8 minutes, and the sum of the task times is 25 minutes. The line will operate for 750 minutes per day.
a. Determine the minimum and maximum cycle times.
b. What range of output is theoretically possible for the line?
c. What is the minimum number of stations needed if the maximum output rate is to be sought?
d. What cycle time will provide an output rate of 300 units per day?


Definitions:

Job Performance

The degree to which an employee accomplishes the tasks, duties, and responsibilities of their job position effectively.

Non-Contingent Punishment

A discipline method where punishment is given irrespective of the behavior's occurrence, not based on specific actions.

Role Ambiguity

The uncertainty experienced by individuals about their responsibilities, expectations, and requirements of their role.

Unfavourable Outcomes

Negative results or consequences that do not meet the desired objectives or expectations.

Related Questions