The owner of a millwork shop is considering three alternative locations for a new plant for building embossed-and-clad steel exterior doors for residences. Fixed and variable costs follow. Since the plant ships nationwide, revenue is assumed the same regardless of plant location. Plot the total cost lines in the chart provided below, and identify the range over which each location is best.  Location  Costs ABC Fixed $700,000$1,000,000$1,1000,000 Variable $28$18$20\begin{array} { | l | c | c | c | } \hline & { \text { Location } } \\\hline \text { Costs } & \mathrm { A } & \mathrm { B } & \mathrm { C } \\\hline \text { Fixed } & \$ 700,000 & \$ 1,000,000 & \$ 1,1000,000 \\\hline \text { Variable } & \$ 28 & \$ 18 & \$ 20 \\\hline\end{array}
 The owner of a millwork shop is considering three alternative locations for a new plant for building embossed-and-clad steel exterior doors for residences. Fixed and variable costs follow. Since the plant ships nationwide, revenue is assumed the same regardless of plant location. Plot the total cost lines in the chart provided below, and identify the range over which each location is best.  \begin{array} { | l | c | c | c | }  \hline & { \text { Location } } \\ \hline \text { Costs } & \mathrm { A } & \mathrm { B } & \mathrm { C } \\ \hline \text { Fixed } & \$ 700,000 & \$ 1,000,000 & \$ 1,1000,000 \\ \hline \text { Variable } & \$ 28 & \$ 18 & \$ 20 \\ \hline \end{array}


Definitions:

Process Layout

A layout that organizes the transformation process into departments that group related processes.

Related Questions