Draw the AOA and AON networks for the following project and calculate the minimum project duration.
 Activity  Duration  (days)  Immediate  Predecessors  A 10 B 8 C 2 A D 4 A E 5 B,C,D\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Duration } \\\text { (days) }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 10 & - - \\\hline \text { B } & 8 & - - \\\hline \text { C } & 2 & \mathrm {~A} \\\hline \text { D } & 4 & \mathrm {~A} \\\hline \text { E } & 5 & \mathrm {~B} , \mathrm { C } , \mathrm { D } \\\hline\end{array}


Definitions:

Environmental Factors

Elements in the external surroundings that can influence an individual's behavior or an organization's performance.

Qualities of Individuals

The characteristics or attributes that define a person’s nature or make up.

Leadership Equation

A conceptual framework or formula that seeks to outline the key factors or elements constituting effective leadership.

Produce Change

Produce change entails creating or initiating transformations within an organization, system, or individual behavior.

Related Questions