Lead Time for Cakes Is 2 Days with Daily Demand 12\frac { 1 } { 2 }

question 4

Multiple Choice

Lead time for cakes is 2 days with daily demand of 10 cakes and a safety stock of 12\frac { 1 } { 2 } a day. Each container (kanban) holds 1 cake. What is the correct number of kanbans?