The Jobs Listed Below Needed to Be Completed A) 476 Days
B) 60

question 119

Multiple Choice

The jobs listed below needed to be completed. Assume that it is now day 140. If the jobs are sequenced according to shortest processing time rule, what is the average completion time?  Job  Processing  Time (days)   Job due date  (days)   A 20180 B 30200 C 10175 D 16230 E 18210\begin{array} { | c | c | c | } \hline \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (days) }\end{array} & \begin{array} { c } \text { Job due date } \\\text { (days) }\end{array} \\\hline \text { A } & 20 & 180 \\\hline \text { B } & 30 & 200 \\\hline \text { C } & 10 & 175 \\\hline \text { D } & 16 & 230 \\\hline \text { E } & 18 & 210 \\\hline\end{array}


Definitions:

Class Inclusion

A cognitive operation that allows a person to see that some classes or sets of objects are subsets of a larger class, and to understand the relationship between the whole and its parts.

Conservation Problems

Issues related to the sustainable management and preservation of natural resources and environments.

Working Memory

A cognitive system responsible for temporarily holding information available for processing, critical for reasoning and the guidance of decision-making and behavior.

Impulse Control

The ability to delay gratification and resist unwanted behaviors or urges.

Related Questions