Fairview Industries is preparing its aggregate plan for the second half of the year. The table below contains monthly demand estimates and working days per month. Complete the table by computing total demand, demand per day (for each month), and the average requirement (in units per day) over the six-month planning horizon. Prepare a graph of forecast demand and level production, by months, for the planning period. Label your graph carefully.
 Month  Expected  Production  Demand per  Tuly 18,000 Days  Day  August 21,00023 September 17,50021 October 12,50021 November 12,00020 December 13,50021 TOTAL \begin{array} { | l | c | c | c | } \hline \text { Month } & \underline { \underline { \text { Expected } } } & \underline { \text { Production } } & \underline { \text { Demand per } } \\\hline \text { Tuly } & 18,000 & \underline { \text { Days } } & \text { Day } \\\hline \text { August } & 21,000 & 23 & \\\hline \text { September } & 17,500 & 21 & \\\hline \text { October } & 12,500 & 21 & \\\hline \text { November } & 12,000 & 20 & \\\hline \text { December } & \underline { 13,500 } & \underline { 21 } & \\\hline \text { TOTAL } & & & \\\hline\end{array}  Fairview Industries is preparing its aggregate plan for the second half of the year. The table below contains monthly demand estimates and working days per month. Complete the table by computing total demand, demand per day (for each month), and the average requirement (in units per day) over the six-month planning horizon. Prepare a graph of forecast demand and level production, by months, for the planning period. Label your graph carefully.   \begin{array} { | l | c | c | c | }  \hline \text { Month } & \underline { \underline { \text { Expected } } } & \underline { \text { Production } } & \underline { \text { Demand per } } \\ \hline \text { Tuly } & 18,000 & \underline { \text { Days } } & \text { Day } \\ \hline \text { August } & 21,000 & 23 & \\ \hline \text { September } & 17,500 & 21 & \\ \hline \text { October } & 12,500 & 21 & \\ \hline \text { November } & 12,000 & 20 & \\ \hline \text { December } & \underline { 13,500 } & \underline { 21 } & \\ \hline \text { TOTAL } & & & \\ \hline \end{array}


Definitions:

Unsafe Behaviours

Actions or practices by individuals that can lead to accidents, injuries, or harm to health.

Workplace Deviance

Behavior that violates organizational norms and can harm the well-being of an organization or its members.

Conscientiousness

Traits that include being orderly, trustworthy, and having a significant dedication to obligations.

Emotional Stability

A personality trait signifying the extent to which a person can remain calm and composed under stress or pressure.