Table 37 -Using Table 3

question 113

Multiple Choice

Table 3.7
 Activity  Immediate  Predecessor (s)  Time  (weeks)  A3 BAC4DA2EA,B4 F A, B,C2GD,E1HE6IE,F2 JG,H,I4 KH,I3 LI6\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \mathrm { A } & \cdots & 3 \\\mathrm {~B} & - \mathrm { A } \\\mathrm { C } & \cdots & 4 \\\\\mathrm { D } & \mathrm { A } & 2 \\\mathrm { E } & \mathrm { A } , \mathrm { B } & 4 \\\mathrm {~F} & \mathrm {~A} , \mathrm {~B} , \mathrm { C } & 2 \\\\\mathrm { G } & \mathrm { D } , \mathrm { E } & 1 \\\mathrm { H } & \mathrm { E } & 6 \\\mathrm { I } & \mathrm { E } , \mathrm { F } & 2 \\\\\mathrm {~J} & \mathrm { G } , \mathrm { H } , \mathrm { I } & 4 \\\mathrm {~K} & \mathrm { H } , \mathrm { I } & 3 \\\mathrm {~L} & \mathrm { I } & 6 \\\hline\end{array}
-Using Table 3.7,suppose activity I is delayed,taking 8 weeks to complete instead of 2 weeks.Assume all other activity times remain the same.How much longer will the total project earliest completion time become?


Definitions:

Historical Order

The sequence of transactions or events documented in past records, often used for analysis and forecasting.

Cost

The amount of money or resources expended to acquire an asset, achieve a goal, or maintain an operation.

Profitability

A measure of the efficiency of a company in generating profits from its operations, typically expressed as net income divided by revenue.

Management Accountants

Professionals who focus on financial reporting and analysis for internal use by business managers to make informed decisions.

Related Questions