Fun Vehicles,Inc.,makes "beach buggies" on an assembly line with 11 work elements.Information on these work elements is as follows:
The company wants to re-balance its line to increase the output to two buggies every three minutes.Use the longest work-element time rule to assign tasks to the workstations.Which of the following is the assignment for the first two stations (S1 and S2) produced by this rule?