You are evaluating two projects.You may accept only one of them.Project one will cost $379,000 initially and will pay $134,000 each year for the next 5 years.Project two will cost $454,000 initially,but will pay $101,000 for the next 10 years.The firm's cost of capital is 15%.Compute the NPV of each project.Which project has the highest NPV and by how much? Round your answers to the nearest dollar.