The Post-Project Review of the Alpha Supplement Project Is Complete

question 106

Multiple Choice

The post-project review of the Alpha Supplement project is complete.It found failures in planning.Too much time was budgeted for market research,leaving not enough time for product development and quality assurance.As a result,the project could not have succeeded even if it had been run perfectly.But there were other problems as well.Constant conflicts between team members demonstrated a failure of leadership.Finally,there were failures in the control function.When component providers failed to deliver,project leaders did not locate and train new providers in time. Which of the following is most strongly suggested by the statements above?