Which of the following statements about measuring intentions is NOT true?


Definitions:

System Nervousness

Frequent changes in an MRP system.

MRP System

Material Requirements Planning (MRP) System is a production planning, scheduling, and inventory control system used to manage manufacturing processes.

Time Fences

Defined periods within a planning horizon during which changes to the schedule can be made with varying degrees of difficulty or restriction.