Given the Portion of the Network Diagram Shown Below,where Numbers

question 79

Multiple Choice

Given the portion of the network diagram shown below,where numbers in boxes show the task times,what is the earliest finish time for task C,if the earliest start time for task A is 10,and the earliest start time for task B is 13? Given the portion of the network diagram shown below,where numbers in boxes show the task times,what is the earliest finish time for task C,if the earliest start time for task A is 10,and the earliest start time for task B is 13?   A) 13 B) 16 C) 20 D) 24


Definitions:

Class Container

A data structure or type that encapsulates multiple elements and provides functionalities for manipulating them, emphasizing the role of organizing and containing data.

Java.awt

Stands for Abstract Window Toolkit, a Java package that provides a set of APIs for creating graphical user interfaces and window-based applications.

Package

A namespace that organizes a set of related classes and interfaces in Java.

Class JFrame

A class in the Java Swing library used for creating a window where components like buttons and text fields can be added.

Related Questions