Plant A is located at the (X, Y) coordinates of (200, 500) and has a volume of shipping of 400 units a day. Plant B is located at the (X, Y) coordinates of (300, 100) and has a volume of shipping of 300 units a day. Using the centroid method, which of the following is the X coordinate for the new plant location?