Consider the diagram presented below.Determine the system reliability if the reliabilities of the individual components are: A = 0.92,B = 0.95,C = 0.93,D = 0.99,E = 0.92,F = 0.90,G = 0.97,H = 0.96.
Subsystem reliabilities:
First (A,B,C): 1 - (1 - 0.92)(1 - 0.95)(1 - 0.93)= 0.99972
Second (D): 0.99
Third (E,F,G,H): 1 - [1 - (0.92)(0.90)][1 - (0.97)(0.96)] = 0.9881664
System reliability = (0.99972)(0.99)(0.9881664)= 0.978011
Customers Served
The number of customers that have been provided with products or services by a business during a specific time period.
Planning Budget
A budget created for a specific level of activity; it helps management set financial targets and evaluate performance.
Customers Served
refers to the number or segment of clients to whom a business has provided products or services within a specific period.
Flexible Budget
A budget that adjusts or flexes with changes in volume or activity level, thereby providing a more useful tool for controlling costs.
Q5: Customer relationship management systems help organizations to
Q9: Improvements in operations are achieved by reducing
Q9: Which of the following is a disadvantage
Q15: The quality assurance team in a firm
Q32: The Malcolm Baldrige Criteria for Performance Excellence
Q33: The commonly used quality tools in the
Q42: The _ step in the DMADV process
Q58: Understanding processes provides the context for determining
Q64: Supply chains help organizations to create a
Q114: Explain the following statement: "Quality cost programs