Use This Earned Schedule Table to Determine the Schedule Variance

question 73

Multiple Choice

Use this earned schedule table to determine the schedule variance ($) for this project at the end of Month 6. Use this earned schedule table to determine the schedule variance ($)  for this project at the end of Month 6.   A)  -$1,460 B)  -$865 C)  $865 D)  $2325