question 93

Multiple Choice

What is the early start time for Activity G given the activity times and precedence requirements shown in the table? What is the early start time for Activity G given the activity times and precedence requirements shown in the table?   A)  22 B)  21 C)  20 D)  19


Definitions:

Managing Suppliers

The process of working effectively with third-party organizations that provide goods and services, to ensure they meet the project's quality, timeline, and budget requirements.

Performance Specifications

Descriptions of the operational requirements and the standards to which a product, service, or project must adhere.

Administrative Function

The tasks related to managing an organization's internal operations, such as record keeping, payroll, and compliance.

Project Administrative

Pertains to the administrative tasks involved in managing a project, including documentation, scheduling, and coordination activities.