question 125

Multiple Choice

Table 10.18
A company desires to set up a line to produce 60 units per hour.
The work elements and their precedence relationships are as follows
 Work  Element  Time (sec)   Immediate  Predecessor(s)  140230135014402562625371538204,59186,710308,9\begin{array} { | c | c | c | } \hline \begin{array} { c } \text { Work } \\\text { Element }\end{array} & \text { Time (sec) } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline 1 & 40 & - - \\2 & 30 & 1 \\3 & 50 & 1 \\4 & 40 & 2 \\5 & 6 & 2 \\6 & 25 & 3 \\7 & 15 & 3 \\8 & 20 & 4,5 \\9 & 18 & 6,7 \\10 & 30 & 8,9 \\\hline\end{array}
-Use the information in Table 10.18. What is the theoretical minimum number of stations versus the number of stations required using the longest work- element time method?

Understand the psychological impact of hospitalization and illness on children and families.
Identify strategies for promoting safety and injury prevention among children and adolescents.
Understand the advantages of computerized accounting systems including error reduction and automatic record updating.
Identify and match accounting and finance terms with their correct definitions.

Definitions:

Material Size

Refers to the physical dimensions of a raw material or component before it is processed or machined into its final form.

Development Drawing

A detailed drawing that provides comprehensive information and specifications for the manufacturing or construction of a part or structure.

Tubular Or Cylindrical

Describes an object having a hollow or solid cylinder shape.

Gage

A device used for measurement or to determine conformity to a set of specifications, often used in manufacturing and engineering to ensure quality and precision.

Related Questions