Application of PERT Network Analysis

question 20

Multiple Choice

Application of PERT Network Analysis
Grace has just graduated from college with a degree in business administration and is totally overwhelmed by her first job. When she was in school, she could work on projects one at a time, and now she finds that she must juggle several projects with multiple activities. Grace is amazed that her supervisor, Linda, seems to have everything planned in a neat flowchart. Linda's current project is to oversee the construction of an office building, and Grace is determined to understand all of the actions that must take place, the major activities, and potential problems so she can be proactive.
-In PERT analysis, the longest or most time- consuming sequence of events and activities required to complete a project in the shortest amount of time is referred to as


Definitions:

Dicta

Comments made by a judge in a court opinion that are not essential to the decision and therefore not legally binding as precedent.

Court's Statements

Official pronouncements or declarations made by a judge or court of law regarding a legal matter or case.

Court's Decision

The final judgment or order given by a court in legal proceedings.

Concurring Opinion

An additional written opinion by a judge who agrees with the decision of the court but wants to make a particular point that was not made or emphasized in the majority opinion.

Related Questions