Consider the following information for the activities comprising a small construction project which is scheduled to complete in 26 days.(Costs are in $1000's.)
 Normal  Schedule Crash Schedule  Activity  Slack  Time  Cost  Time  Cost  M 0710419 II 25656 O 047212 P 059313 Q 22516 R 04949 S 0612515\begin{array}{cccccc}&&\text { Normal }&\text { Schedule}&\text { Crash}&\text { Schedule }\\\text { Activity } & \text { Slack } & \text { Time } & \text { Cost } & \text { Time } & \text { Cost } \\\text { M } & 0 & 7 & 10 & 4 & 19 \\\text { II } & 2 & 5 & 6 & 5 & 6 \\\text { O } & 0 & 4 & 7 & 2 & 12 \\\text { P } & 0 & 5 & 9 & 3 & 13 \\\text { Q } & 2 & 2 & 5 & 1 & 6 \\\text { R } & 0 & 4 & 9 & 4 & 9 \\\text { S } & 0 & 6 & 12 & 5 & 15\end{array} A.If the project must be completed in 25 days, which activity should be accelerated? Why?
B.Will the critical path be altered?
C.What is the total estimated cost of the project on the accelerated 25 day schedule?


Definitions:

College Student Samples

Research participants who are college or university students, often used in psychological and social studies.

Subdiscipline

A specialized field or area that is part of a broader discipline.

Children

Young human beings below the age of puberty or below the legal age of majority.

Psychology

The scientific study of the mind and behavior, exploring facets of human and non-human animal functions including perceptions, cognition, emotion, personality, behavior, and interpersonal relationships.

Related Questions