Exhibit 15 -Refer to Exhibit 15

question 46

Essay

Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
 Activity  Days  Required  Predecessar  Activities  A 5B3 A  C 4 A  D 7B,CE6 C F5 E G4 D. F \begin{array} { c c c } \text { Activity } & \begin{array} { c } \text { Days } \\\text { Required } \end{array} & \begin{array} { c } \text { Predecessar } \\\text { Activities }\end{array} \\\hline \text { A } & 5 & - \\B & 3 & \text { A } \\\text { C } & 4 & \text { A } \\\text { D } & 7 & B , C \\E & 6 & \text { C } \\F & 5 & \text { E } \\G & 4 & \text { D. F }\end{array}
-Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
 A  B  C DEFGHI1 Activity  Description  Predlecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 5050503 B  Activity B  A 358101354 C  Activity C  A 4595905 D  Activity D  B,C 7916132046 E  Activity E  C 691591507 F  Activity F  E 51520152008 G  Activity G  D, F 4202420240\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predlecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 5 & 0 & 5 & 0 & 5 & 0 \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 5 & 8 & 10 & 13 & 5 \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 4 & 5 & 9 & 5 & 9 & 0 \\\hline 5 & \text { D } & \text { Activity D } & \text { B,C } & 7 & 9 & 16 & 13 & 20 & 4 \\\hline 6 & \text { E } & \text { Activity E } & \text { C } & 6 & 9 & 15 & 9 & 15 & 0 \\\hline 7 & \text { F } & \text { Activity F } & \text { E } & 5 & 15 & 20 & 15 & 20 & 0 \\\hline 8 & \text { G } & \text { Activity G } & \text { D, F } & 4 & 20 & 24 & 20 & 24 & 0 \\\hline\end{array}


Definitions:

Car Rental

A service industry that provides temporary use of vehicles to customers for a short period of time, often ranging from a few hours to weeks.

Hydroelectric Dam

A structure that uses the energy from flowing water to generate electricity, capitalizing on water cycle and gravitational forces.

Lattes

A coffee drink made with espresso and steamed milk, often served with foam on top.

Gift Card

A prepaid debit card loaded with a specific amount of money, which can be used as a gift and is redeemable for purchases at specified retailers.

Related Questions