The Project Manager Is Evaluating Options to Complete the Project

question 79

Essay

The project manager is evaluating options to complete the project early so that the company can earn a bonus. He has determined that the project schedule can be compressed into a six-month schedule, with the same total number of worker-months. In that case, the staffing requirements are as shown below. The project manager is evaluating options to complete the project early so that the company can earn a bonus. He has determined that the project schedule can be compressed into a six-month schedule, with the same total number of worker-months. In that case, the staffing requirements are as shown below.   Develop an optimal staffing plan for the project under the accelerated schedule. Develop an optimal staffing plan for the project under the accelerated schedule.


Definitions:

Unity of Direction

A management principle suggesting that all parts of an organization should be aligned and moving towards common objectives.

Home Building Company

A business organization that specializes in constructing residential homes for clients.

Complete Autonomy

The state or condition of being entirely independent, with the freedom to make decisions without external control or influence.

Pig Iron

A form of crude iron that is the direct product of smelting iron ore with coke and limestone in a blast furnace.

Related Questions