Examlex

Solved

Members of a Project Team Have Developed a Schedule for an Upcoming

question 1

Multiple Choice

Members of a project team have developed a schedule for an upcoming IT project. They observe that two activities, A. Hardware Design and B. Software Design, must be complete before a third activity, C. Testing, can begin. Hardware and Software Design share the same predecessor task, and each one is estimated to have a duration of 4 weeks. Based on historical data, team members estimate that activity A and activity B each has an 80% chance of finishing within the estimated time frame. Which of the following is true?


Definitions:

Deming's Principles

A set of management practices to help companies increase their quality and productivity.

Patient Safety

The reduction of risk of unnecessary harm associated with healthcare to an acceptable minimum.

Redesign of Delivery

The restructuring of healthcare service methods and modalities to improve quality, efficiency, and patient outcomes.

Official Joint Commission

An independent, non-profit organization that accredits and certifies healthcare organizations and programs in the United States to ensure compliance with specific standards.