What Is the Critical Chain in the Schedule Below

question 3

Multiple Choice

What is the critical chain in the schedule below?
What is the critical chain in the schedule below?      A)  A-B-D-F-G B)  A-C-E-G C)  A-B-D-E-G D)  A-B-D-E-F-G E)  ABDFG F)  None of the above