Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
 Job  Processing Time (days)   Due Date  A 511 B 616 C 319 D 410 E 29\begin{array} { | l | l | l | } \hline \text { Job } & \text { Processing Time (days) } & \text { Due Date } \\\hline \text { A } & 5 & 11 \\\hline \text { B } & 6 & 16 \\\hline \text { C } & 3 & 19 \\\hline \text { D } & 4 & 10 \\\hline \text { E } & 2 & 9 \\\hline\end{array}
Using the earliest due date (EDD) rule, the average lateness for the five jobs is:


Definitions:

Rivalry

The competitive relationship between firms in the market, striving to gain advantage over each other in terms of sales, market share, or innovation.

Nonexcludable

A characteristic of a good or service whereby it is not possible to prevent people who have not paid for it from having access to it.

Free-rider Problem

A situation in which individuals benefit from resources, goods, or services without paying for them, leading to underprovision of those goods or services.

Public Goods

Goods that are non-excludable and non-rivalrous, meaning that anyone can consume them without diminishing their availability to others, such as public parks and clean air.

Related Questions