question 18

Multiple Choice

Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
 Job  Processing Time (days)   Due Date A812B49C36D77E520\begin{array} { | l | l | l | } \hline \text { Job } & \text { Processing Time (days) } & \text { Due Date } \\\hline \mathrm { A } & 8 & 12 \\\hline \mathrm { B } & 4 & 9 \\\hline \mathrm { C } & 3 & 6 \\\hline \mathrm { D } & 7 & 7 \\\hline \mathrm { E } & 5 & 20 \\\hline\end{array}
Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is _____.


Definitions:

Nonverbal Messages

Communication that involves transmitting messages without using words, including gestures, body language, facial expressions, and tone of voice.

Albert Mehrabian

A psychologist renowned for his work on non-verbal communication and the 7%-38%-55% rule regarding the elements of effective communication.

Speaker

An individual who delivers a speech or presentation to an audience.

Listener

An individual who actively engages in hearing and processing information that is being communicated by another person or source.

Related Questions