____ Is Used to Schedule Big Projects, Production and Operations

question 27

Short Answer

____ is used to schedule big projects, production and operations managers break complex operations into smaller tasks and estimates the time needed to complete the key tasks.This scheduling system was developed in the 1950s for building and maintaining chemical plants.