Timber Enterprises purchased 67,000 pounds (cost = $616,400) of direct material to be used in the manufacture of the company's only product. According to the production specifications, each completed unit requires four pounds of direct material at a standard cost of $9 per pound. Direct materials consumed by the end of the period totaled 65,500 pounds in the manufacture of 16,050 finished units.
An examination of Timber's payroll records revealed that the company worked 42,000 labor hours (cost = $621,600) during the period, and specifications called for each completed unit requiring 2.6 hours of labor at a standard cost of $15 per hour.
Assume that the company computes variances at the earliest point in time.
Required:
Calculate the direct-material price and quantity variances, and the direct-labor rate and efficiency variances. Indicate whether each variance is favorable or unfavorable.
Hypotheses
Proposed explanations or predictions for phenomena or relationships, subject to testing and verification through scientific research.
Thematic Apperception Test
A projective psychological test that involves presenting individuals with ambiguous scenes and asking them to make up stories about them, used to assess their underlying thoughts, feelings, and themes.
Ambiguous Pictures
Images that can be interpreted in multiple ways due to their vague or unclear content.
Psychological Problems
Psychological problems encompass a range of mental health conditions that affect mood, thinking, and behavior.
Q11: Republic Resorts owns numerous hotels on each
Q15: Consider the following comments about absorption- and
Q28: A profit center manager:<br>A) does not have
Q36: Which of the following is not an
Q36: Quinton Company has set the following standards
Q52: Fort Smith's per-unit inventoriable cost under variable
Q53: The direct-material price variance is:<br>A) $2,880U.<br>B) $2,920F.<br>C)
Q58: Responsibility accounting systems strive to:<br>A) place blame
Q95: Which of the following would have no
Q107: A budgeted income statement, a budgeted balance