Examlex

Solved

________ Functions Perform Arithmetic Operations,such as Calculating Averages and Totals,on

question 61

Short Answer

________ functions perform arithmetic operations,such as calculating averages and totals,on records displayed in a table or query.


Definitions:

Critical Path

The sequence of tasks that determines the minimum project duration; delaying any task on this path delays the whole project.

Project Duration

The total period from the start to the completion of a project.

Negative Total Float

The amount of time that needs to be saved on a project schedule to meet the deadline, indicating a project is behind schedule.

Concrete

A construction material composed of cement, water, aggregates (sand and gravel), and possibly admixtures, used for building a wide range of structures.