A Project Has Four Activities: A, B, C, and D

question 80

Multiple Choice

A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for the project?


Definitions:

Resource Opportunism

The practice of exploiting circumstances and opportunities with minimal regard for principles or consequences in order to gain access to resources.

Revolutionary Action

An act or series of acts aimed at overthrowing a government or social system.

Resource Mobilization

The process of gathering assets, both financial and non-financial, to support and achieve specific goals and objectives, often in the context of social movements.

Non-routine Collective Action

Collaborative efforts that occur outside the norm or established patterns, often in response to unique or emergent situations.

Related Questions