You Have Collected the Data for a Time-Cost CPM Scheduling

question 62

Multiple Choice

You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project  direct costs  are given here. <sub> </sub>   The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,What is the total (i.e., direct and indirect)  project cost? A)  $2,150 B)  $2,300 C)  $2,400 D)  $2,450 E)  $2,500 The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,What is the total (i.e., direct and indirect) project cost?


Definitions:

Work Motivation

The set of internal and external forces that influence an individual's level of interest and commitment to perform their job effectively.

Job Simplification

The process of breaking down a job into its simplest components and removing complex or unnecessary tasks to increase efficiency.

Operating Efficiency

A measure of the effectiveness with which an organization uses its resources to produce goods or services.

Permanent Part-Time Work

Refers to employment positions that are not full-time but still offer a consistent, ongoing work schedule.

Related Questions