A Project Has Four Activities: A, B, C, and D

question 1

Multiple Choice

A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity D?


Definitions:

Actual Output

The real, measurable production achieved by a company, device, or process, as opposed to projected or theoretical capacities.

Scheduling Customers

Scheduling customers involves allocating specific times and resources for serving customers in various contexts, such as appointments or deliveries, to enhance efficiency and customer satisfaction.

Workforce

The group of individuals who are currently employed or are available for employment, including both full-time and part-time workers.

Capacity Decision

Choices made by a company regarding the amount of resources it will commit to meet demand for its products or services.

Related Questions