A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWP for Activity C?
Staying The Same
Maintaining an unchanged state or position over a period of time.
Motivational Dynamics
The study of the forces and processes that drive individuals to behave in certain ways, often focusing on the interplay between different motivations.
Drive-Reduction Theory
A psychological theory that posits that motivation arises from the desire to reduce an uncomfortable state of tension caused by unmet needs.
Homeostasis
The method through which living beings maintain a steady and unchanging state by controlling their internal surroundings.
Q16: Learning curves can be applied to individuals
Q16: The time duration in which capacity planning
Q18: A learning curve shows the increase in
Q22: A project layout is only used for
Q24: Delivering is not considered in supply chain
Q25: Mr. Goldratt's "theory of constraints" is useful
Q28: The objective of strategic capacity planning is
Q36: A matrix project attempts to blend properties
Q38: For the purposes of assembly-line balancing, cycle
Q85: Which of the following is not an