Assume That Activity G Has the Following Times: Early Start

question 60

Multiple Choice

Assume that activity G has the following times: Early start time = 7 days
Early finish time = 13 days
Late start time = 15 days
Late finish time = 21 days
Which of the following statements is True about activity G?