A Simple CPM Network Has Three Activities, A, B, and C

question 64

Multiple Choice

A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=5.